Southwest Engineering v. United States

From wikilawschool.net. Wiki Law School does not provide legal advice. For educational purposes only.
Southwest Engineering v. United States
Court 8th Circuit
Citation 341 F.2d 998
Date decided March 1, 1965

Facts

  • Southwest Engineering Co. ="Southwest" = plaintiff = a construction contractor
  • United States = the federal government = defendant
  • In the 1960s, Southwest & the United States signed 4 contracts with liquidated damages clauses specifying that damages would accrue at a set daily rate for each day the project was late
  • Southwest was late in completing all 4 projects
  • The United States determined that Southwest owed $8,300 in liquidated damages which would be subtracted from Southwest's payments

Procedural History

  • Southwest sued the United States opposing the assessment of liquidated damages.
  • The United States won a summary judgment.

Issues

Is a liquidated damages clause un-enforceable if a contractor's delay in completing a construction project doesn't result in actual damages?

(The United Statement admitted that it didn't sustain damages when the 4 contracts were completed late.)

Holding

No. A liquidated damages clause may be enforced even if the contractor's delay didn't result in actual damages.

Judgment

Affirmed

Rule

Judge Van Oosterhout: The amount of the liquidated damages must be reasonable to be sustained in a court of law; in this case, the aforesaid amount was indeed reasonable.

Resources