Southwest Engineering v. United States
From wikilawschool.net. Wiki Law School does not provide legal advice. For educational purposes only.
Southwest Engineering v. United States | |
Court | 8th Circuit |
---|---|
Citation | 341 F.2d 998 |
Date decided | March 1, 1965 |
Facts
- Southwest Engineering Co. ="Southwest" = plaintiff = a construction contractor
- United States = the federal government = defendant
- In the 1960s, Southwest & the United States signed 4 contracts with liquidated damages clauses specifying that damages would accrue at a set daily rate for each day the project was late
- Southwest was late in completing all 4 projects
- The United States determined that Southwest owed $8,300 in liquidated damages which would be subtracted from Southwest's payments
Procedural History
- Southwest sued the United States opposing the assessment of liquidated damages.
- The United States won a summary judgment.
Issues
Is a liquidated damages clause un-enforceable if a contractor's delay in completing a construction project doesn't result in actual damages?
(The United Statement admitted that it didn't sustain damages when the 4 contracts were completed late.)Holding
No. A liquidated damages clause may be enforced even if the contractor's delay didn't result in actual damages.
Judgment
Affirmed
Rule
Judge Van Oosterhout: The amount of the liquidated damages must be reasonable to be sustained in a court of law; in this case, the aforesaid amount was indeed reasonable.
Resources