New Era v. Forster

From wikilawschool.net. Wiki Law School does not provide legal advice. For educational purposes only.
New Era v. Forster
Court New York Court of Appeals
Citation 86 N.E.2d 757
Date decided June 3, 1949

Facts

  • New Era Homes Corp. = "New Era" = plaintiff = a construction firm
  • Forster = defendant = person who hired "New Era" for home renovation
  • The total price in the contract was $3,075
    1. $150 at contract signing
    2. $1,000 at delivery of materials
    3. $1,500 rough work
    4. $425 upon completion
  • New Era commenced the construction project.
  • Forster made the 1st 2 payments.
  • At the work stage, Forster refused to make the 3rd payment.

Procedural History

  • New Era sued Forster.
  • New Era demanded $1,500 for the rough work.
  • Forster accepted his default on the contract.
  • The jury awarded New Era $1,500.
  • New Era also won in the Appellate Division.

Issues

Is a contract with periodic partial payments divisible such that each payment is consideration for a specified portion of the contract?


(Installment contract) =? (divisible contract)

Arguments

Forster argued that he should be allowed to pay less than $1,500 for the rough work.

Holding

No. A contract with periodic partial payments is an entire contract with 1 consideration for the full job.

  • New Era can either
    1. collect in quantum meruit or
    2. for the value it had lost

Judgment

Reversed

Reasons

In a construction contract, the separate payments aren't allocated to separate components of the job. In these construction contracts, 1 whole contract exist. Thus, you cannot take that 1 contract & creates separate sub-contracts.


The builder can sue to collect in quantum meruit (1 option).

Rule

Resources