Peevyhouse v. Garland

From wikilawschool.net. Wiki Law School does not provide legal advice. For educational purposes only.
(Redirected from Peevyhouse v. Garland Coal and Mining Co.)
Peevyhouse v. Garland
Court Oklahoma Supreme Court
Citation 382 P.2d 109, cert. denied, 375 U.S. 906, 84 S.Ct. 196, 11 L.Ed.2d 145
Date decided May 28, 1963

Facts

  • In 1954, the Peevyhouse couple owned acres of land in Oklahoma containing rich coal deposits.
  • Mr. & Mrs. Peevyhouse = "Peevyhouse" = plaintiff
  • Garland Coal Mining Co. = "Garland" = defendant
  • Garland wanted to lease the Peevyhouse in order to mine the coal
  • Plaintiff contracted with defendant coal mining company to allow them to use Peevyhouse’s land (60 acres) in excavating a coal vein. The contract was for 5 years.
  • In the contract, Garland specifically agreed to perform certain restorative and remedial work at the end of the contract.
  • The work would involve moving many thousands of yards of dirt, a cost estimated to be about $29,000, while the improvement to the land was estimated at only $300.
  • Garland employed the strip mining technique. At the end of the 5 years, Garland refused to restore the land to its original condition.

Procedural History

  • Peevyhouse sued Garland for breach of contract.
  • Garland's expert testified that it restoration cost would be $29,000 while increasing the land value by only $300.
  • Verdict for plaintiffs in the amount of $5,000, only a fraction of the cost of performance.
  • The $5,000 the jury awarded Peevyhouse exceeded the cost of the farm in 1962.

Issues

  • Must the breaching party (Garland) pay the full cost of performance ($29,000), if that cost greatly exceeds the total economic value of full performance ($300)?
  • Whether the damages should be limited to
    • the difference in the value of the land or
    • to the cost of the remedial work defendant agreed to do.

Arguments

Garland argued that the court should limit damages to $300.

Holding

In a 5 to 4 decision: If the cost of performance is grossly dis-proportionate to the economic benefit, the defendant should only pay the economic benefit.

Judgment

for Peevyhouse for $300

Reasons

  • The cost of performance is the proper measure of damages if it does not involve unreasonable economic waste.
  • Where the defect in material or construction is incidental to the main purpose of the contract & one that cannot be remedied without an expenditure for re-construction disproportionate to the end to be attained, the value rule should be followed.
  • Sometimes, the full cost of performance is an economic waste!

Rule

Justice Jackson: The proper way to calculate damages is by looking at the relative economic benefit.