Victoria Laundry (Windsor) Ltd. v. Newman Industries Ltd.

From wikilawschool.net. Wiki Law School does not provide legal advice. For educational purposes only.
Revision as of 14:06, October 19, 2011 by Lost Student (talk | contribs) (Created page with "'''Facts''': Plaintiff ran a laundry business and purchased a large boiler from Defendant. The delivery was significantly delayed. Plaintiff sued for lost profits for a lucrativ...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)

Facts: Plaintiff ran a laundry business and purchased a large boiler from Defendant. The delivery was significantly delayed. Plaintiff sued for lost profits for a lucrative contract it missed out on due to the delay.

Holding: Held for Plaintiff.

Reason: Even though the purpose of the boiler was not expressed, it is easily foreseeable. The loss arose naturally from the breach.